500 Ton Sedimen Diangkat Dari Kali Krukut Petogogan

500 Tons of Krukut River Sediment Transported

The South Jakarta Sub-dept. of Water Management began to dredge sediment in Krukut River, Petogogan Urban Village, South Jakarta as rainy season anticipation.

The dredging was done along 200 meters width and two meters depth

About 500 tons of sediment were transported from the river since Monday (7/27) to Thursday (7/30).

"The dredging was done along 200 meters width and two meters depth," said Suyadi, Head Section of Flood Control System Maintenance for South Jakarta Water Management Sub-department, Friday (7/31).

2 Excavators Sent to Krukut River as Flood Anticipation

Relaying on beritajakarta.com observation, there were two excavators deployed to dredge the sediment.

"Our target is dredging 1,500 meters within 1.5 months. The dry sediment will be transported to Ancol coal fired power plant (PLTU) area," he disclosed.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1416 personFolmer
  2. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye852 personAldi Geri Lumban Tobing
  3. Commemorating Vesak, Jakarta Lights Up with Illumination of Jakarta 2026

    access_time30-05-2026 remove_red_eye653 personBudhi Firmansyah Surapati
  4. Seniors Participate in Pasti Bisa Berkarya at MRT Stations

    access_time02-06-2026 remove_red_eye602 personAldi Geri Lumban Tobing
  5. Krendang Fire Victims Receive Proper Support and Assistance

    access_time29-05-2026 remove_red_eye475 personBudhi Firmansyah Surapati